| About CementPal |
| A clear non-yellowing penetrating acrylic resin formulated to protect and enhance the
appearance of concrete, exposed aggregate driveways, interlocking paving stones, patio
slabs, concrete blocks, mortar slate, flagstone, terrazzo and stamped concrete.
CementPal is available in two finishes.
Surface must be clean, dry and free of any loose matter or other contaminants. Driveways and patios should be clear of weeds or
vegetation. Algae, mold and mildew should be removed using a chlorine bleach solution orWoodPal Quick and Easy Cleaner. Grease
or oil, which has penetrated into the substrate, should be removed using a grease spot remover. Any cracks or damaged areas should be
repaired and fully cured before coating. Ideally, surfaces should be power washed, but a thorough wash using a pressure tip on a garden
hose is acceptable. Before coating, allow the surface to dry.
This new technology is water based and will have a milky appearance in the can and when first applied. When properly applied this
milky look turns to a clear, shiny, and tough protective coating.
This coating requires specific conditions during application to achieve desired results.
Do not apply when the temperature is below 10 degrees C (50 Degrees F ) or greater than 30 degrees C (86 Degrees F ).
Do not apply in the direct sun if possible. If it is necessary to apply on a warm day in direct sun slightly dampen the surface to be sealed
with a fine spray of water just prior to application.
Do not apply if the weather forecast calls for rain or dew within 8 hours of the expected completion of your project.
Brush and roller (10 mm (3/8”) pile roller is ideal, an extension pole will make application easier). Air, airless or a low pressure spray
such as a garden sprayer fitted with a spray nozzle should be used. Product should be applied liberally to horizontal surfaces; after 5
minutes, excess product should be redistributed. For vertical surfaces, start at the base and work upwards to prevent unevenness from
runs. Two coats recommended on new surfaces.
Dry times at 21 Degrees C/ 70 Degrees F relative humidity 40- 60%. To touch: 45 minutes, To Overcoat: 4 hours. Allow 4 hours prior
to light foot traffic. Allow 3 days dry time before subjecting surface to heavy vehicular traffic.
Number of coats. Two generous coats are recommended.
Approximately 14 to 20 sq. meters per 3.78 L (150 to 225 sq. feet per Gal.) depending on porosity of surface.
Clean tools and application equipment with warm soapy water immediately after use. Dispose of containers as per local regulations.
Recommended annually.
Recommended every 3 years. |
|
|